Probe begins into Indore-Patna Express derailment that claimed 145 lives
Hindustan Times | ByOliver Fredrick, Pukhrayan (kanpur Dehat)
Nov 21, 2016 01:42 PM IST
The commissioner of railway safety reached Pukhrayan, the site of the accident, nearly 32 hours after tragedy struck around 3:10am on Sunday. North Central Railway (NCR) officials confirmed that commissioner of railway safety (Eastern) PK Acharya was inspecting the scene.
A high-level probe into the derailment of 14 coaches of the Indore-Patna Express train here that killed 145 people began on Monday.
Commissioner of railway safety (Eastern) PK Acharya inspects the wreckage of the Indore-Patna Express, which derailed near Kanpur, on Monday.(HT Photo)
The commissioner of railway safety reached Pukhrayan, the site of the accident, nearly 32 hours after tragedy struck around 3:10am on Sunday. North Central Railway (NCR) officials confirmed that commissioner of railway safety (Eastern) PK Acharya was inspecting the scene.
Commissioner of railway safety (Eastern) PK Acharya pulled up officials for negligence. (HT Photo)
The commissioner pulled up officials for negligence, pointing out corroded parts of one of the damaged bogies. He has seized 18 such parts for investigation. The entire inspection was recorded on video.
The tracks were being examined to look into the possibility of a crack having caused India’s worst train tragedy in six years. Other possible causes will also be investigated.
Officials say cracks on the track are a common phenomenon in winter.
A National Disaster Response Force (NDRF) official said the possibility of finding survivors in the wreckage was bleak, even as rescue operations continued on Monday.
The NCR officials said track restoration work would start only after the rescue efforts have ended.
Commissioner of railway safety (Eastern) PK Acharya arrived at the site of the accident on Monday. (HT Photo)
“The NDRF men are at work. Two bogies are still lying on the railway track and they need to be removed. The high tension lines and the track need to be fixed. It will take another 12 hours to restore train movement on this track on the Kanpur-Jhansi route,” said Amit Malaviya, public relations officer, NCR.
Four trains were cancelled and 14 others were diverted on Sunday.