Bridge design was vetted by IIT-Delhi team, says Bihar dept

By, Patna
Jul 16, 2023 10:04 PM IST

The court has conducted two hearings of the case while August 12 has been fixed as the date for the hearing

The design of the bridge in Bihar — which collapsed on June 4 — was vetted and approved by Indian Institute of Technology, Delhi (IIT-Delhi), the state road construction department (RCD) said in a reply to the Patna high court.

The 3.15-km-long bridge being built on river Ganga between Aguanighat in Khagaria district and Sultanganj in Bhagalpur district collapsed on June 4 (ANI)
The 3.15-km-long bridge being built on river Ganga between Aguanighat in Khagaria district and Sultanganj in Bhagalpur district collapsed on June 4 (ANI)

The 3.15-km-long bridge being built on river Ganga between Aguanighat in Khagaria district and Sultanganj in Bhagalpur district collapsed in first week of June.

The RCD filed the affidavit, a copy of which HT has seen, while replying to a petition filed by Congress leader Lalan Kumar and two others before the high court. The petitioners have sought blacklisting of the construction company and judicial or CBI inquiry into the matter. The court has conducted two hearings of the case while August 12 has been fixed as the date for the hearing.

“The drawing and design submitted by the designing consultant of the contractor was vetted by IIT-Delhi and communicated to the Bihar Rajya Pul Nirman Nigam Limited (BRPNN), the state government’s executing agency,” noted the RDC affidavit filed in the court on July 13.

The IIT-Roorkee experts, who were roped in by the RCD, after first partial collapse of the bridge on April 30 last year, attributed it to “gross design failure”. The experts in their report to the state government said that “the NDT (non-destructive test) of the entire span done by IIT-Roorkee also indicates some discrepancies in the bridge geometry.... The application of shims and unplanned wet stitches have been recommended by the designer. While it has been communicated regularly that these practices may have debilitating consequences on the structure, it has been maintained that the design is robust enough to incorporate these changes,” said the report.

The spans on pier 10-12 of the four-lane extradosed cable stayed bridge, being built by SP Singla Construction Limited at the cost of 1,710 crore, had caved in the mainstream of Ganga like pack of cards.

The IIT-Roorkee experts pointed out that nature of the first partial collapse on pier number 5 and those on other three piers was similar, for which the project designer, McElhanney Consultancy, Canada, was apprised about.

The RCD engineers, however, argued that they were constrained to intervene as the construction company was building the project in engineering, procurement and construction (EPC) mode. The Bihar Rajya Pul Nirman Nigam Limited (BRPNNL) was confident about robustness of the design after the experts of the IIT-Delhi approved the drawing and design of the bridge as proof consultant. “Since the bridge construction is very specialised in nature (construction of cable stayed and extradosed bridge), that’s why experts from different countries and as well as from India were engaged as part of authority engineers,” read the counter affidavit of the RCD.

BRPNNL officials said that the preliminary report of the IIT-Roorkee experts had recommended for design review of the entire bridge portion and hence the design consultant was called to explain its various aspects on June 6, a day after the collapse. The IIT-Roorkee experts, comprising Mahesh Tandon and Vinay Gupta, had ruled out concrete weakness for the fall. “Segment 9 seems to be interface between right part and the flexible portion of the span. This could be the reason why the failure was triggered from this location,” they said.

“As per our original conjecture, the root cause of both failures (on April 30, 2022 and June 4, 2023) seems primarily to be a failure of match casting. The failure is endemic as the segments in pier 5 and the segments that failure recently were cast in different casting yards on opposite sides of the river. In both the spans, unplanned wet stitches are commonly seen. Shims have also been applied regularly to overcome geometric differences due to match casting,” the experts’ report said.

The RCD in the counter-affidavit said that the additional chief secretary is conducting the inquiry and would submit its report within two months (by August 6). “In view of the complex nature of the project, it would be apt that the considered view is taken by the state government on consideration of entire materials,” the affidavit stated.

Tell us what your First Vote will stand for in a short video & get a chance to be featured on HT’s social media handles. Click here to know more!

Stay updated Bihar Lok Sabha Result and with all the Breaking News and Latest News from Bengaluru. Click here for comprehensive coverage of top cities including Delhi, Mumbai, Hyderabad, and more across India . Stay informed on the latest happenings in World News.
Tell us what your First Vote will stand for in a short video & get a chance to be featured on HT’s social media handles. Click here to know more!

Stay updated Bihar Lok Sabha Result and with all the Breaking News and Latest News from Bengaluru. Click here for comprehensive coverage of top cities including Delhi, Mumbai, Hyderabad, and more across India . Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
SHARE
Story Saved
Live Score
Saved Articles
Following
My Reads
Sign out
New Delhi 0C
Tuesday, May 06, 2025
Follow Us On